Time-Cost Tradeoff for Optimizing Contractor NPV by Cost Payment and Resource Constraints Using NSGA-II Algorithm (Case Study:Bandar Abbas Gas Condensate Refinery Project)
Author/Authors
Zareei، M. نويسنده Department of Industrial Engineering, Faculty of Engineering, Imam Hossein University, Tehran, Iran , , Hassan-Pour، H.A. نويسنده Department of Industrial Engineering, Faculty of Engineering, Imam Hossein University, Tehran, Iran , , Mosadegh-Khah، M. نويسنده Department of Industrial Engineering, Faculty of Engineering, Imam Hossein University, Tehran, Iran ,
Issue Information
روزنامه با شماره پیاپی سال 2014
Pages
15
From page
12
To page
26
Abstract
In this paper, a mathematical model is presented for project scheduling with multiple purposes based on considering cost payment and resource constrains and since this this problem is considered as complex optimization in NP-Hard context, in order to solve proposed method from NSGA-II algorithm and the results are compared with GAMS software in some problems. The proposed method is a Converge to the optimum and efficient solution algorithm. Besides this algorithm is used in some parts of refinery project.
Journal title
The Journal of Mathematics and Computer Science(JMCS)
Serial Year
2014
Journal title
The Journal of Mathematics and Computer Science(JMCS)
Record number
1435441
Link To Document