• Title of article

    Time-Cost Tradeoff for Optimizing Contractor NPV by Cost Payment and Resource Constraints Using NSGA-II Algorithm (Case Study:Bandar Abbas Gas Condensate Refinery Project)

  • Author/Authors

    Zareei، M. نويسنده Department of Industrial Engineering, Faculty of Engineering, Imam Hossein University, Tehran, Iran , , Hassan-Pour، H.A. نويسنده Department of Industrial Engineering, Faculty of Engineering, Imam Hossein University, Tehran, Iran , , Mosadegh-Khah، M. نويسنده Department of Industrial Engineering, Faculty of Engineering, Imam Hossein University, Tehran, Iran ,

  • Issue Information
    روزنامه با شماره پیاپی سال 2014
  • Pages
    15
  • From page
    12
  • To page
    26
  • Abstract
    In this paper, a mathematical model is presented for project scheduling with multiple purposes based on considering cost payment and resource constrains and since this this problem is considered as complex optimization in NP-Hard context, in order to solve proposed method from NSGA-II algorithm and the results are compared with GAMS software in some problems. The proposed method is a Converge to the optimum and efficient solution algorithm. Besides this algorithm is used in some parts of refinery project.
  • Journal title
    The Journal of Mathematics and Computer Science(JMCS)
  • Serial Year
    2014
  • Journal title
    The Journal of Mathematics and Computer Science(JMCS)
  • Record number

    1435441