    Payment scheduling under project crashing based on project progress

  • Author/Authors

    Mortazavi Nejad ، Marziye - Ferdowsi University of Mashhad , Tareghian ، Hamed Reza - Ferdowsi University of Mashhad , Sari ، zeynab - Ferdowsi University of Mashhad

  • Pages
    18
  • From page
    39
  • To page
    56
  • Abstract
    In this paper, we address a new problem in the context of project payment scheduling when project activities are allowed to be crashed with the purpose of maximizing the contractors net present value (NPV). We assume that the contractor is paid at some prespecified points of time according to the volume of work performed. Upon completion of activities, the cost of their execution is paid. Two different approaches are used to determine the volume of work performed at so called review points. In the first approach, only completed activities are considered. In the second approach, any portions of the activities that are executed are considered. To increase the volume of work performed at the review points, the contractor may decide to crash some activities and as such possibly increases his NPV. As activity crashing costs the contractor money, a compromise needs to be made. Two mathematical models are developed to study each approach and hence help the contractor to make the best decision. These models offer a means of investigating whether it is advisable to crash some activities and are therefore of practical importance. It is shown that the contractor may increase his NPV, even when he pays for the activity crashing costs. The performance of the mathematical models is illustrated using a numerical example.
  • Keywords
    Payment scheduling , Progress payment , Project crashing , Contractor’s net present value.
  • Journal title
    Iranian Journal of Numerical Analysis and Optimization
  • Serial Year
    2017
  • Journal title
    Iranian Journal of Numerical Analysis and Optimization
  • Record number

    2440874