First decade of large-power gas turbines in Nigeria
Author/Authors
H. I. Hart، نويسنده ,
Issue Information
روزنامه با شماره پیاپی سال 1995
Pages
10
From page
213
To page
222
Abstract
This is an appraisal of the performance of the four 75 MW gas turbines (GTs), i.e. the first large-power generating GTs installed in Nigeria. All the major parameters considered—availability, utilization and capability factors—were much lower than acceptable. The frequency of failures of some vital components of the machines is also higher than normal. The general low performance is linked to some peculiar environmental conditions of the place and circumstances of the country, which make the design of certain parts of the GTs inadequate.