A two-phase fuzzy programming model for a complex bi-objective no-wait flow shop scheduling
Author/Authors
Naderi-Beni، Mahdi نويسنده , , Tavakkoli-Moghaddam، Reza نويسنده , , Naderi، Bahman نويسنده , , Ghobadian، Ehsan نويسنده , , Pourrousta، Alireza نويسنده ,
Issue Information
دوفصلنامه با شماره پیاپی 10 سال 2012
Pages
10
From page
617
To page
626
Abstract
In this paper, we study no-wait flow shop problem where setup times depend on sequence of operations. The proposed problem considers sequence-independent removal times, release date with an additional assumption that there are some preliminary setup times. There are two objectives of weighted mean tardiness and makespan associated with the proposed model of this paper. We formulate the resulted problem as a mixed integer programming, where a two-phase fuzzy programming is implemented to solve the model. To examine the performance of the proposed model, we generate several sample data, randomly and compare the results with other methods. The preliminary results indicate that the proposed two-phase model of this paper performed relatively better than Zimmermanʹs single-phase fuzzy method.
Journal title
International Journal of Industrial Engineering Computations
Serial Year
2012
Journal title
International Journal of Industrial Engineering Computations
Record number
674382
Link To Document