Resource constrained scheduling simulation model for alternative stochastic network projects Original Research Article
Author/Authors
Dimitri Golenko-Ginzburg، نويسنده , , Aharon Gonik، نويسنده , , Zohar Laslo، نويسنده ,
Issue Information
روزنامه با شماره پیاپی سال 2003
Pages
13
From page
105
To page
117
Abstract
The paper presents a heuristic for resource constrained network project scheduling. A network project comprising both alternative deterministic decision nodes and alternative branching nodes with probabilistic outcomes is considered. Several renewable activity related resources, such as machines and manpower, are imbedded in the model. Each type of resource is in limited supply with a resource limit that is fixed at the same level throughout the project duration. Each activity in the project requires resources of various types with fixed capacities. The activity duration is a random variable with given density function.
Keywords
Resource constrained GERT project scheduling algorithm , Probabilistic branching , Alternative decision nodes , Stochastic project simulation , Renewable resources , Joint variant
Journal title
Mathematics and Computers in Simulation
Serial Year
2003
Journal title
Mathematics and Computers in Simulation
Record number
854049
Link To Document