• Title of article

    Minimizing the mean weighted absolute deviation from due dates in lot-streaming flow shop scheduling

  • Author/Authors

    Suk-Hun Yoon، نويسنده , , Jose A. Ventura، نويسنده ,

  • Issue Information
    دوهفته نامه با شماره پیاپی سال 2002
  • Pages
    15
  • From page
    1301
  • To page
    1315
  • Abstract
    Lot-streaming is the process of splitting a job (lot) into a number of smaller sublots so that successive operations can be overlapped in a multi-stage production system. This paper presents a procedure for minimizing the mean weighted absolute deviation from due dates when jobs are scheduled in a lot-streaming flow shop. This performance criterion has been shown to be non-regular and requires a search among schedules with inserted idle times to find an optimal solution. For a given job sequence, we present linear programming formulations to obtain optimal sublot completion times for cases where buffers between successive machines have limited or infinite capacities, and sublots have equal-size or are consistent. A no-wait flow shop problem is also considered. Sixteen pairwise interchange methods are considered to generate the best sequences. These algorithms are obtained by combining four rules to generate initial sequences with four neighborhood search mechanisms. Computational experiments are conducted on 140 test problems. The results show that the best solutions are obtained by the heuristic algorithm with a non-adjacent pairwise interchange method and the smallest overall slack time rule to generate the initial sequence.
  • Keywords
    Scheduling , Flow shop , Mean weighted absolute deviation , Pairwise interchange method , Lot-streaming
  • Journal title
    Computers and Operations Research
  • Serial Year
    2002
  • Journal title
    Computers and Operations Research
  • Record number

    927283