    Combining contemporaryandtraditionalprojectmanagementtoolsto resolve aprojectschedulingproblem

  • Author/Authors

    John E. Hebert، نويسنده , , RichardF.Deckro ، نويسنده ,

  • Issue Information
    ماهنامه با شماره پیاپی سال 2011
  • Pages
    12
  • From page
    21
  • To page
    32
  • Abstract
    In thispaperweexamineaconstructionprojectinvolvingthebuildingoflargeconcreteslabsforthree buildingsinanofficeparkcomplex.Therearefinish-to-start(FS)aswellasstart-to-start(SS)andfinish- to-finish (FF)precedencerelationshipsamongtheprojectactivities.Weprepareaninitialproject scheduleusingMicrosoftProjectandmanuallyvalidatetheresultsusingtheprecedencediagramming method(PDM)procedure.Whentheclientinformsusthattheschedulemustbeshortenedwefindthat MicrosoftProjectdoesnothavethecapabilityforresolvingourparticulartime/costtradeoffissues.So we reverttothetraditionalapproachforresolvingtime/costtradeoffsinprojectsanddevelopan originallinearprogrammingformulationforthetime/costtradeoffproblemwhenaprojectismodeled as aprecedencediagram.Bycombiningcontemporary(MicrosoftProject)andtraditional(alinear programmingtime/costtradeoffmodel)projectmanagementtoolsweareabletosuccessfullyresolve the schedulingissuesassociatedwiththeslabconstructionproject.Further,wedemonstratethe anomalouseffectsofstart-to-start(SS)andfinish-to-finish(FF)relationshipsviaourconstruction projectexampleinwhichthesolutiontothetime/costtradeoffproblemrequiresthatcertainactivities be lengthenedinordertoshortentheprojectduration.
  • Keywords
    Project Management , Precedence diagrams , Time/cost tradeoff , Linear programming
  • Journal title
    Computers and Operations Research
  • Serial Year
    2011
  • Journal title
    Computers and Operations Research
  • Record number

    927831