• Title of article

    Earliness–tardiness scheduling with setup considerations

  • Author/Authors

    Francis Sourd، نويسنده ,

  • Issue Information
    ماهنامه با شماره پیاپی سال 2005
  • Pages
    17
  • From page
    1849
  • To page
    1865
  • Abstract
    The one-machine scheduling problem with sequence-dependent setup times and costs and earliness–tardiness penalties is addressed. A time-indexed formulation of the problem is presented as well as different relaxations that give lower bounds of the problem. Then, a branch-and-bound procedure based on one of these lower bounds is presented. The efficiency of this algorithm also relies on new dominance rules and on a heuristic to derive good feasible schedules. Computational tests are finally presented.
  • Keywords
    Earliness–tardiness scheduling , Setup times , MIP formulation , Heuristics , branch-and-bound
  • Journal title
    Computers and Operations Research
  • Serial Year
    2005
  • Journal title
    Computers and Operations Research
  • Record number

    928253