DocumentCode
1177234
Title
Equipment Qualification: The Process for New Plants as Seen by a Utility
Author
Porter, Newell S.
Author_Institution
Washington Public Power Supply System
Issue
7
fYear
1984
fDate
7/1/1984 12:00:00 AM
Firstpage
1654
Lastpage
1655
Abstract
The qualification process, based on the experience an electric utility gained through its efforts to meet the requirements of IEEE Standards 627-80 and 323-1974 and the attendant regulatory guidance for new plants, is presented. Important aspects of each step from initial plant design to maintaining equipment qualification during operations are described. Although all these steps are not directly applicable to near-term and operating plants, the guidance offered is generally appropriate for procurement of qualified spare and replacement parts and for plant modifications of safety systems.
Keywords
Design engineering; Nuclear power generation; Power generation; Power industry; Power supplies; Procurement; Qualifications; Safety devices; Senior members; Testing;
fLanguage
English
Journal_Title
Power Apparatus and Systems, IEEE Transactions on
Publisher
ieee
ISSN
0018-9510
Type
jour
DOI
10.1109/TPAS.1984.318648
Filename
4112725