• DocumentCode
    1185828
  • Title

    BPA 1100 kV Transmission System Development-Planning, Program, and Objectives

  • Author

    Gens, Ralph S. ; Gehrig, Eward H. ; Eastvedt, Robert B.

  • Author_Institution
    Bonneville Power Administration
  • Issue
    6
  • fYear
    1979
  • Firstpage
    1916
  • Lastpage
    1923
  • Abstract
    This paper summarizes current system planning studies for application of 1100 kV to the Pacific Northwest transmission system, the associated test and development program, and construction of two test lines. It compares 500 and 1100 kV costs and shows 1100 kV to be economical at loadings above 4,000-5,000 MW. The two test lines consist of 1200 kV Lyons Electrical Prototype Line at Lyons, Oregon, and the 1200 kV Moro Mechanical Test Line at Moro, Oregon.
  • Keywords
    Distributed parameter circuits; Insulation testing; Power generation; Power generation economics; Power transmission; Power transmission lines; Prototypes; Substations; System testing; Voltage;
  • fLanguage
    English
  • Journal_Title
    Power Apparatus and Systems, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0018-9510
  • Type

    jour

  • DOI
    10.1109/TPAS.1979.319371
  • Filename
    4113708