• DocumentCode
    1524723
  • Title

    Optimal maintenance scheduling in a parallel redundant system consisting of series components in each branch

  • Author

    Billinton, Roy ; Pan, Jun

  • Author_Institution
    Power Syst. Res. Group, Saskatchewan Univ., Saskatoon, Sask., Canada
  • Volume
    14
  • Issue
    3
  • fYear
    1999
  • fDate
    7/1/1999 12:00:00 AM
  • Firstpage
    928
  • Lastpage
    933
  • Abstract
    A set of equations is developed in this paper and used in conjunction with the minimal cut set method to evaluate the total failure frequency of a parallel redundant system consisting of series components in each branch where each component can operate in its wearout period and the failure rate of each component is not constant. The optimum maintenance intervals are determined based on the criterion that the total failure frequency of the system is minimized. The Newton-Raphson method is applied to obtain the unknown optimum maintenance intervals for the system. The proposed approach is presented and illustrated using a practical substation example
  • Keywords
    Newton-Raphson method; maintenance engineering; optimisation; power system planning; scheduling; substations; Newton-Raphson method; failure rate; maintenance scheduling optimisation; minimal cut set method; optimum maintenance intervals; parallel redundant system; power systems; substations; total failure frequency; wearout period; Density functional theory; Distribution functions; Equations; Frequency; Hazards; Newton method; Power system reliability; Power systems; Preventive maintenance; Substations;
  • fLanguage
    English
  • Journal_Title
    Power Delivery, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0885-8977
  • Type

    jour

  • DOI
    10.1109/61.772336
  • Filename
    772336