• DocumentCode
    1681994
  • Title

    Switching operations in a high voltage substation correlated with overvoltages generated in the low voltage internal service network

  • Author

    Agoris, D. ; Karagiannopoulos, C. ; Panos, G. ; Pyrgioti, E.

  • Author_Institution
    Dept. of Electr. & Comput. Eng., Patras Univ., Greece
  • fYear
    1999
  • Firstpage
    144
  • Abstract
    Due to problems caused to electronic devices, fed by 220 V auxiliary circuit in a 400 kV substation of the Greek HV interconnected system, extensive measurements of overvoltages have been performed, correlated with the timing of switching operations in the primary circuit of 400 kV. The investigated cases were the opening of incoming circuit breaker, the closing of coupling circuit breaker between busbars, the opening and closing of the circuit breaker of a reactor and the simultaneous opening of two coupling circuit breakers. The waveforms of the overvoltages recorded between phase and neutral had duration of about 100-200 /spl mu/s and a decaying oscillation of about 500 kHz, while their crest values were up to 6.4 kV. The overvoltages recorded between neutral and earth had values only up to 200 V.
  • Keywords
    circuit breakers; overvoltage; power system interconnection; substations; switching; switching transients; 100 to 200 mus; 220 V; 400 kV; 500 kHz; 6.4 kV; Greece; HV interconnected system; HV substation; LV internal service network; busbars; circuit breaker; overvoltage generation; overvoltage waveforms; switching operations; Circuit breakers; Coupling circuits; Inductors; Interconnected systems; Performance evaluation; Substations; Surges; Switching circuits; Timing; Voltage;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Electric Power Engineering, 1999. PowerTech Budapest 99. International Conference on
  • Conference_Location
    Budapest, Hungary
  • Print_ISBN
    0-7803-5836-8
  • Type

    conf

  • DOI
    10.1109/PTC.1999.826575
  • Filename
    826575