• DocumentCode
    1774513
  • Title

    Load restoration optimization during last stage of network reconfiguration

  • Author

    Hanbing Qu ; Maolin Yin ; Shan Lin

  • Author_Institution
    Shandong Jinan Power Supply Co., Jinan, China
  • fYear
    2014
  • fDate
    23-26 Sept. 2014
  • Firstpage
    1075
  • Lastpage
    1079
  • Abstract
    During last stage of network reconfiguration after major blackout, loads should be picked up in sequence with considering certain constraints, which is a multi-constraint, non-linearity, integer programming problem. This paper proposes a combinatorial optimization model with considering the sequencing problem of load pickup, in which effects of pickup sequence are taken into consideration in both objective function and constraints. As the large optimization scale of restorable loads during last stage of network reconfiguration, a new adaptive particle swarm optimization algorithm is adopted to solve the proposed model. Case studies performed on the actual Shandong power system demonstrate that the proposed model effectively reflects sequencing problem and the adopted algorithm can satisfy the practical requirement on computation speed.
  • Keywords
    integer programming; particle swarm optimisation; power system restoration; Shandong power system; adaptive particle swarm optimization algorithm; combinatorial optimization model; integer programming problem; load pick up sequencing problem; load restoration optimization; network reconfiguration; Abstracts; Electricity; Load modeling; Mathematical model; Substations; adaptive particle swarm optimization algorithm; combinatorial optimization; load restoration; power system restoration; sequencing problem;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Electricity Distribution (CICED), 2014 China International Conference on
  • Conference_Location
    Shenzhen
  • Type

    conf

  • DOI
    10.1109/CICED.2014.6991870
  • Filename
    6991870