DocumentCode
1774513
Title
Load restoration optimization during last stage of network reconfiguration
Author
Hanbing Qu ; Maolin Yin ; Shan Lin
Author_Institution
Shandong Jinan Power Supply Co., Jinan, China
fYear
2014
fDate
23-26 Sept. 2014
Firstpage
1075
Lastpage
1079
Abstract
During last stage of network reconfiguration after major blackout, loads should be picked up in sequence with considering certain constraints, which is a multi-constraint, non-linearity, integer programming problem. This paper proposes a combinatorial optimization model with considering the sequencing problem of load pickup, in which effects of pickup sequence are taken into consideration in both objective function and constraints. As the large optimization scale of restorable loads during last stage of network reconfiguration, a new adaptive particle swarm optimization algorithm is adopted to solve the proposed model. Case studies performed on the actual Shandong power system demonstrate that the proposed model effectively reflects sequencing problem and the adopted algorithm can satisfy the practical requirement on computation speed.
Keywords
integer programming; particle swarm optimisation; power system restoration; Shandong power system; adaptive particle swarm optimization algorithm; combinatorial optimization model; integer programming problem; load pick up sequencing problem; load restoration optimization; network reconfiguration; Abstracts; Electricity; Load modeling; Mathematical model; Substations; adaptive particle swarm optimization algorithm; combinatorial optimization; load restoration; power system restoration; sequencing problem;
fLanguage
English
Publisher
ieee
Conference_Titel
Electricity Distribution (CICED), 2014 China International Conference on
Conference_Location
Shenzhen
Type
conf
DOI
10.1109/CICED.2014.6991870