Productivity Simulation During the Planning Phase of the Glencoe Tunnel in Calgary, Canada: A Case Study
Author
Al-Battaineh, H.T. ; AbouRizk, Simaan ; Tan, James ; Fernando, Siri
Author_Institution
Dept. Civil & Environ. Eng., Alberta Univ., Edmonton, Alta.
fYear
2006
fDate
3-6 Dec. 2006
Firstpage
2087
Lastpage
2092
Abstract
This paper discusses the Glencoe Storm Sewer Upgrade Project in Calgary, Alberta. The proposed tunnel is 2920 mm in diameter, stretching along 27th Ave SW from 15th St SW to 20th St SW with a total length of 935 m. Its depth varies from 16 m at the working shaft to 42 m at the retrieval shaft. The tunnel will reduce surface flooding by providing temporary storage of stormwater runoff during major storm events. The focus of this paper is project planning. The planning phase includes scope definition, contract setup, cost estimate, team assembly, equipment and material procurements, risk analysis, constructability review, geotechnical investigation, Safety and ECO Plan development, and scheduling and productivity simulations. The challenges presented in this project are the unfamiliarity with the local conditions and the uncertainty of the projected productivity and completion date of the project. Those issues were modeled and mitigation strategies were established using simulation technologies
Keywords
facilities planning; productivity; project management; structural engineering computing; tunnels; 2920 mm; 935 m; Glencoe Storm Sewer Upgrade Project; Glencoe tunnel; productivity simulation; project planning; stormwater runoff; surface flooding; Assembly; Contracts; Costs; Floods; Phase estimation; Procurement; Productivity; Risk analysis; Shafts; Storms;
fLanguage
English
Publisher
ieee
Conference_Titel
Simulation Conference, 2006. WSC 06. Proceedings of the Winter
Conference_Location
Monterey, CA
Print_ISBN
1-4244-0500-9
Electronic_ISBN
1-4244-0501-7
Type
conf
DOI
10.1109/WSC.2006.322997
Filename
4117855
Link To Document