Title
Monitoring of a large scale event in the Brazilian Power System by WAMS
Author
Decker, I.C. ; Agostini, M.N. ; e Silva, A.S. ; Dotta, D.
Author_Institution
Fed. Univ. of Santa Catarina, Florianópolis, Brazil
fYear
2010
fDate
1-6 Aug. 2010
Firstpage
1
Lastpage
8
Abstract
On November 10, 2009 a fault at the AC Itaipu transmission system led to a large scale blackout of the Brazilian Interconnected Power System (BIPS) with a 40% load loss. This event was recorded at outlet voltage by a synchronized phasor measurement prototype, the LVPMS, with PMUs (Phasor Measurement Units) installed in nine universities throughout Brazil. The recorded data contain relevant information on the events leading to the blackout and the BIPS restoration.
Keywords
power system interconnection; power system measurement; power transmission faults; AC Itaipu transmission system; BIPS restoration; Brazilian interconnected power system; WAMS; data recording; large scale blackout; large scale event monitoring; outlet voltage; synchronized phasor measurement prototype; wide area system monitoring; Load flow; Oscillators; Phasor measurement units; Power transmission lines; Prototypes; Transmission line measurements; Voltage measurement; PMU; Phasor measurements; Power system monitoring; WAMS; Wide-area monitoring;
fLanguage
English
Publisher
ieee
Conference_Titel
Bulk Power System Dynamics and Control (iREP) - VIII (iREP), 2010 iREP Symposium
Conference_Location
Rio de Janeiro
Print_ISBN
978-1-4244-7466-0
Electronic_ISBN
978-1-4244-7465-3
Type
conf
DOI
10.1109/IREP.2010.5563249
Filename
5563249
Link To Document