• DocumentCode
    2128433
  • Title

    Modelling of a combined cycle conversion using Simulink

  • Author

    Scott, P.H. ; Russell, J.P.

  • Author_Institution
    Parsons Turbine Generators Ltd., UK
  • Volume
    1
  • fYear
    1994
  • fDate
    21-24 March 1994
  • Firstpage
    368
  • Abstract
    Tenaga Nasional Generating Authority of Malaysia has decided to upgrade the existing steam turbo-generating plant to a more efficient combined cycle plant. Parsons Turbine Generators Ltd. (PTGL) were to supply one steam turbine and the necessary control equipment for a combined cycle system. The control of combined cycle plant was known to be a difficult task, involving the efficient sharing of load between the gas and the steam turbines, the limiting of ramping rates, and the control of boiler steam pressures. Simulink package was used to model the associated plant and to aid the design of a control strategy for the combined cycle plant.
  • Keywords
    CAD; combined cycle power stations; control engineering computing; digital simulation; gas turbines; power engineering computing; steam turbines; CAD; Malaysia; Parsons Turbine Generators; Simulink; Tenaga Nasional Generating Authority; boiler steam pressures; combined cycle plant; control equipment; digital simulation; gas turbine; load sharing; ramping rates; steam turbine;
  • fLanguage
    English
  • Publisher
    iet
  • Conference_Titel
    Control, 1994. Control '94. International Conference on
  • Conference_Location
    Coventry, UK
  • Print_ISBN
    0-85296-610-5
  • Type

    conf

  • DOI
    10.1049/cp:19940160
  • Filename