In order to satisfy growing electrical demand in the San Diego, California area, San Diego Gas and Electric Company (SDG&E) is modifying existing transmission towers to maximize right of way utilization. Recent projects include modifying existing 138-kV towers to 230-kV capacity. Design considerations including construction methods, and electrical and structural requirements are discussed
Keywords
poles and towers; 138 to 230 kV; SDG&E; San Diego Gas and Electric Company; San Diego, California; construction methods; electrical demand; electrical requirements; right of way utilization; structural requirements; transmission towers; Bridge circuits; Conductors; Costs; Distributed parameter circuits; Insulator testing; Lattices; Plastic insulation; Poles and towers; Transmission lines; Voltage;
fLanguage
English
Publisher
ieee
Conference_Titel
Transmission and Distribution Conference and Exhibition, 2005/2006 IEEE PES
Conference_Location
Dallas, TX
Print_ISBN
0-7803-9194-2
Type
conf
DOI
10.1109/TDC.2006.1668663
Filename
1668663
Link To Document