• DocumentCode
    2405315
  • Title

    Increase the capacity of a 12 kV/4.16 kV secondary selective substation at a large refinery, design, implementation and commissioning

  • Author

    Ramirez, Roderick R. ; Gaynor, Paul ; Johnson, Gregory G. ; Sauer, Steven ; Ritter, Tyson

  • Author_Institution
    ExxonMobil, Torrance, CA, USA
  • fYear
    2011
  • fDate
    19-21 Sept. 2011
  • Firstpage
    1
  • Lastpage
    10
  • Abstract
    This paper will detail the processes in the design, revamp and commissioning of an existing 12 kV-4.16 kV 15 MVA secondary-selective substation for a major refinery with its N-1 capacity already exceeded due to load creep. The project installs a third 15 MVA transformer with associated switchgear, bus ducts, protection and transfer control system. The paper will briefly outline the conceptual plan and engineering for the project. The primary focus of the paper will be to detail the effort in modification of the existing power system configuration, developing a startup and commissioning plan, factory acceptance testing, and the actual startup and commissioning. The management directive was to complete a “flawless” startup and commissioning of the substation within a compressed refinery turnaround window. A flawless startup was important to management because a functional failure in a main electrical substation was unacceptable. The business cost of such a failure could easily exceed the capital cost of the substation. It was deemed as cost effective by management and engineering personnel to insure that the design, construction and testing of the substation was as thorough as possible. The design was completed by one team and reviewed by the fresh eyes of a completely independent team. The paper will review important tests performed during the startup and commissioning, along with the benefits and usefulness it provided. The complicated system was checked by the vendor, checked again by the startup team, and then completely checked for functionality at the end user´s facility. The testing included the normal functional and secondary injection testing, but additionally used primary injection to test relays and CTs and test certain relay functions. The paper will conclude with a discussion of the lessons learned during the testing.
  • Keywords
    commissioning; failure analysis; power transformer protection; substations; switchgear; testing; N-1 capacity; apparent power 15 MVA; bus ducts; commissioning; compressed refinery turnaround window; electrical substation functional failure; factory acceptance testing; power system configuration; secondary injection testing; secondary selective substation; switchgear; test certain relay functions; test relays; transfer control system; transformer; voltage 12 kV; voltage 4.16 kV; Circuit faults; Generators; Programming; Protective relaying; Substations; Switchgear; Substation; load creep; protective relaying; switchgear;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Petroleum and Chemical Industry Conference (PCIC), 2011 Record of Conference Papers Industry Applications Society 58th Annual IEEE
  • Conference_Location
    Toronto, ON
  • ISSN
    0090-3507
  • Print_ISBN
    978-1-61284-299-8
  • Type

    conf

  • DOI
    10.1109/PCICon.2011.6085897
  • Filename
    6085897