  • Title

    Modification of in-service substation based on IEC 61850

  • Author

    Renhui, Dou ; Jing, Yu ; Jianfeng, Lu

  • Author_Institution
    Electric Power Research Institute, China
  • fYear
    2012
  • fDate
    23-26 April 2012
  • Firstpage
    1
  • Lastpage
    5
  • Abstract
    The standard IEC 61850 contributes the manufacturers and the end users. But it also makes many obstacles to the modification of the conventional substation. This paper presents a scheme which modifies an in-service conventional substation gradually to a modern substation which conforms to IEC 61850 standards. The procedure of the modification is divided into three stages. During the first stage, all the preparations have been finished. All the configurations and joint tests have been done before shipment. The secondary stage is to construct the substation network. New Human Machine Interface (HMI) and communication gateway will replace the old ones. They simultaneously support protocol of the existing system and IEC 61850 standards. The third stage is the modification of the bay level devices. The old cabinets and the cables out of the cabinets are kept. The inner IEDs are replaced. The connections between the IEDs and the cabinets also need to be re-arranged. The modification of bay can be done one by one according to the overhaul plan. The process is stable and secure, and it won´t affect the normal operation of the substation.
  • Keywords
    IEC standards; Logic gates; Protocols; Relays; Substation automation; IEC 61850; in-service; retrofit; substation;
  • fLanguage
    English
  • Publisher
    iet
  • Conference_Titel
    Developments in Power Systems Protection, 2012. DPSP 2012. 11th International Conference on
  • Conference_Location
    Birmingham, UK
  • Print_ISBN
    978-1-84919-620-8
  • Type

    conf

  • DOI
    10.1049/cp.2012.0050
  • Filename
    6227538