  • Abstract
    In this paper, enhanced lambda iteration (ELI) algorithm is developed for solving the economic dispatch (ED) problem of thermal units considering generator constraints for a lossless system. In classical lambda iteration technique, improper selection of initial value of lambda (incremental cost) may cause slow convergence and thus leads to divergence. The presented algorithm is capable of handling the problem by considering the concept of equal incremental cost criterion for deciding the value of initial lambda and also the equality and inequality constraints are handled easily. The algorithm is tested on small and large scale thermal generating units showing the feasibility of the algorithm.
  • Keywords
    optimisation; power generation dispatch; power generation economics; thermal power stations; enhanced lambda iteration algorithm; incremental cost criteria; large scale economic dispatch problem; thermal generating units; Convergence; Economics; Generators; Heuristic algorithms; Optimization; Power generation; Power systems; economic dispatch; generator fuel cost; incremental cost; lagrangian multiplier; power demand;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Recent Advances and Innovations in Engineering (ICRAIE), 2014
  • Conference_Location
    Jaipur
  • Print_ISBN
    978-1-4799-4041-7
  • Type

    conf

  • DOI
    10.1109/ICRAIE.2014.6909294
  • Filename
    6909294