Abstract
The paper shows the switching behaviour of a grid circuit breaker in case of short circuits close to generator terminals. For the simulation a new three-phase circuit breaker model has been developed in the network calculation program Power-Factory. PowerFactory is an appropriate software to simulate the switching behaviour of a circuit breaker.
Keywords
Circuit breakers; Circuit simulation; DSL; Delay; Page description languages; Power generation; Power system dynamics; Power system modeling; Power system simulation; Switching circuits; Circuit breaker; PowerFactory; power plant; pre-strikes; short circuit; simulation model;
fLanguage
English
Publisher
ieee
Conference_Titel
Environment and Electrical Engineering (EEEIC), 2010 9th International Conference on
Conference_Location
Prague, Czech Republic
Print_ISBN
978-1-4244-5370-2
Electronic_ISBN
978-1-4244-5371-9
Type
conf
DOI
10.1109/EEEIC.2010.5489961
Filename
5489961
Link To Document