• DocumentCode
    2891449
  • Title

    Commissioning of the spallation neutron source accelerator systems

  • Author

    Plum, M.A.

  • Author_Institution
    Oak Ridge Nat. Lab., Oak Ridge
  • fYear
    2007
  • fDate
    25-29 June 2007
  • Firstpage
    2603
  • Lastpage
    2607
  • Abstract
    The Spallation Neutron Source accelerator complex consists of a 2.5 MeV H" front-end injector system, a 186 MeV normal-conducting linear accelerator, a 1 GeV superconducting linear accelerator, an accumulator ring, and associated beam transport lines. The linac was commissioned in five discrete runs, starting in 2002 and completed in 2005. The accumulator ring and associated beam transport lines were commissioned in two runs from January to April 2006. With the completed commissioning of the SNS accelerator, the facility has begun initial low-power operations. In the course of beam commissioning, most beam performance parameters and beam intensity goals have been achieved at low duty factor. A number of beam dynamics measurements have been performed, including transverse coupling in the ring, beam instability thresholds, and beam distributions on the target. The commissioning results, achieved beam performance and initial operating experience of the SNS will be discussed.
  • Keywords
    linear accelerators; neutron sources; particle accelerators; SNS accelerator; accumulator ring; beam dynamics; spallation neutron source accelerator; superconducting linear accelerator; Laboratories; Linear accelerators; Linear particle accelerator; Neutrons; Optical coupling; Particle beam injection; Particle beams; Structural beams; Superconducting devices; US Department of Energy;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Particle Accelerator Conference, 2007. PAC. IEEE
  • Conference_Location
    Albuquerque, NM
  • Print_ISBN
    978-1-4244-0916-7
  • Type

    conf

  • DOI
    10.1109/PAC.2007.4440722
  • Filename
    4440722