  • Abstract
    The cost of interconnection is an important factor in Non Utility Generator (NUG) overall project costs. This cost has to be minimized without compromising the safety or reliability of the transmission system. The lowest cost interconnection is a transmission line tap. However, low cost taps may negatively impact transmission system performance and protection system performance. The negative impacts can often be mitigated with increasing complexity (and cost) of the interconnection. This paper describes BC Hydro´s experience with studying interconnection proposals, using internally developed protection criteria to minimize costs while retaining acceptable protection performance.
  • Keywords
    cost reduction; power system interconnection; power system protection; transmission networks; BC Hydro; NUG; costs minimization; nonutility generators; power system interconnection; protection system performance; transmission network; transmission system performance; Circuit faults; Generators; Integrated circuit interconnections; Power quality; Power transmission lines; Reliability; Sensitivity; Power system interconnection; Tap transmission connection;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Innovative Smart Grid Technologies - Asia (ISGT Asia), 2013 IEEE
  • Conference_Location
    Bangalore
  • Print_ISBN
    978-1-4799-1346-6
  • Type

    conf

  • DOI
    10.1109/ISGT-Asia.2013.6698706
  • Filename
    6698706