    Entropy-based scheduling of resource-constrained construction projects

  • Author/Authors

    Christodoulou، نويسنده , , Symeon and Ellinas، نويسنده , , Georgios and Aslani، نويسنده , , Pooyan، نويسنده ,

  • Issue Information
    روزنامه با شماره پیاپی سال 2009
  • Pages
    10
  • From page
    919
  • To page
    928
  • Abstract
    A method is presented for resource allocation and scheduling of resource-constrained projects by use of a measure of the projectsʹ entropy. The entropy, as a measure of the degree of disorder in a system, is an indicator of a projectʹs tendency to progress out of order and into a chaotic condition and it can thus serve to forecast a projectʹs development. The entropy metric used in the analysis is based on the resource assignments per activity (required vs. assigned resource units).
  • Keywords
    Resource-constrained construction scheduling , entropy