A genetic algorithm-based method for look-ahead scheduling in the finishing phase of construction projects
Author/Authors :
Dong، نويسنده , , Ning and Ge، نويسنده , , Dongdong and Fischer، نويسنده , , Martin and Haddad، نويسنده , , Zuhair، نويسنده ,
Issue Information :
روزنامه با شماره پیاپی سال 2012
Pages :
12
From page :
737
To page :
748
Abstract :
Genetic algorithms (GAs) are widely used in finding solutions for resource constrained multi-project scheduling problems (RCMPSP) in construction projects. In the finishing phase of a complex construction project, each room forms a confined space for crews to conduct a series of activities and can thus be considered as an individual sub-project. Generating the look-ahead schedule (LAS) which takes into account the limited resources available at the job site falls in the domain of RCMPSP. Therefore GAs can be used to address this scheduling problem and help construction managers to guide the daily work on site. However, current GAs do not consider three key practical aspects that the project planers and construction managers deal with frequently at the job sites: the engineering priorities of each individual sub-project, the zone constraint and the blocking constraint. By addressing these aspects, this paper proposes a GA-based method that takes them into account in the search process for optimum project duration and/or cost. Two examples are used for the discussion of the effectiveness of this method and to showcase its capability in project scheduling when the scale of a project increases.
Keywords :
genetic algorithm (GA) , Look-ahead schedule (LAS) , RCPSP , SIMULATION , RCMPSP