Title of article :
Time-Cost Tradeoff for Optimizing Contractor NPV by Cost Payment and Resource Constraints Using NSGA-II Algorithm (Case Study:Bandar Abbas Gas Condensate Refinery Project)
Author/Authors :
Zareei، M. نويسنده Department of Industrial Engineering, Faculty of Engineering, Imam Hossein University, Tehran, Iran , , Hassan-Pour، H.A. نويسنده Department of Industrial Engineering, Faculty of Engineering, Imam Hossein University, Tehran, Iran , , Mosadegh-Khah، M. نويسنده Department of Industrial Engineering, Faculty of Engineering, Imam Hossein University, Tehran, Iran ,
Issue Information :
روزنامه با شماره پیاپی سال 2014
Pages :
15
From page :
12
To page :
26
Abstract :
In this paper, a mathematical model is presented for project scheduling with multiple purposes based on considering cost payment and resource constrains and since this this problem is considered as complex optimization in NP-Hard context, in order to solve proposed method from NSGA-II algorithm and the results are compared with GAMS software in some problems. The proposed method is a Converge to the optimum and efficient solution algorithm. Besides this algorithm is used in some parts of refinery project.
Journal title :
The Journal of Mathematics and Computer Science(JMCS)
Serial Year :
2014
Journal title :
The Journal of Mathematics and Computer Science(JMCS)
Record number :
1435441
Link To Document :
بازگشت