Modeling construction time in Spanish building projects
Author/Authors :
Guerrero، نويسنده , , Miguel A. and Villacampa، نويسنده , , Yolanda and Montoyo، نويسنده , , Andrés، نويسنده ,
Issue Information :
ماهنامه با شماره پیاپی سال 2014
Pages :
13
From page :
861
To page :
873
Abstract :
The literature states that project duration is affected by various scope factors. Using 168 building projects carried out in Spain, this paper uses the multiple regression analysis to develop a forecast model that allows estimating project duration of new builds. The proposed model uses project type, gross floor area (GFA), the cost/GFA relationship and number of floors as predictor variables. The research identified the logarithmic form of construction speed as the most appropriate response variable. GFA has greater influence than cost on project duration but both factors are necessary to achieve a forecast model with the highest accuracy. We developed an analysis to verify the stability of forecasted values and showed how a model with high values of fit and accuracy may display an anomalous behavior in the forecasted values. The sensitivity of the proposed forecast model was also analyzed versus the variability of construction costs.
Keywords :
Construction speed , Regression analysis , Forecasting , Time , Building projects , Construction Cost
Journal title :
International Journal of Project Management
Serial Year :
2014
Journal title :
International Journal of Project Management
Record number :
1840873
Link To Document :
بازگشت