• Title of article

    The Longest Path Problem in Fuzzy Project Networks: A Case Study

  • Author/Authors

    El-Santawy ، Mohamed F. - Cairo University , Abd-Allah ، Soha M. - Cairo University

  • Pages
    11
  • From page
    97
  • To page
    107
  • Abstract
    In This article a real-life international construction and building project network problem is presented, the problem of identifying the critical path of the project within fuzzy parameters (the longest path) is formulated by applying a linear programming approach which incorporates the concept of α-cuts into two (primal and dual) models. In order to determine the solution a code was developed to solve 22 linear programming models that had been constructed at different α-cuts during formulation. Yager’s ranking method is applied to compare all paths, and determining the time of the longest one.
  • Keywords
    Construction Building , Critical Path , Fuzzy CPM , Linear Programming , Project Management ,
  • Journal title
    General Mathematics Notes
  • Serial Year
    2011
  • Journal title
    General Mathematics Notes
  • Record number

    2457404