Title of article :
A New Analysis of Critical Paths in Mega Projects with Interval Type-2 Fuzzy Activities By Considering Time, Cost, Risk, Quality, and Safety Factors
Author/Authors :
Dorfeshan, Yahya Department of Industrial Engineering - Faculty of Engineering - Shahed University, Tehran , Mousavi, Meysam Department of Industrial Engineering - Faculty of Engineering - Shahed University, Tehran , Vahdani, Behnam Department of Industrial Engineering, Faculty of Industrial and Mechanical Engineering - Islamic Azad University Qazvin Branch, Qazvin
Pages :
16
From page :
145
To page :
160
Abstract :
Critical path method (CPM) is categorized as a popular tool for scheduling mega projects. In this paper, to enjoy the advantages of interval type-2 fuzzy sets (IT2FSs) and better address uncertainty for the activities’ attributes, a new analysis model is presented to determine the critical path under an IT2F-environment. Also, new efficient factors on specifying critical paths, such as time, cost, risk, safety, and quality (TCRSQ), are presented to achieve a more robust plan assisting in megaproject success. Moreover, an IT2F weighting approach is suggested for specifying the weights of TCRSQ factors. Furthermore, a new IT2F-approach employing the relative preference relation is expressed for identifying the importance of each expert. Consequently, a new model for critical path determination procedure by considering efficient factors is developed under the IT2FSs environment. Finally, to demonstrate the suggested model's capability and the calculation process, an application from the previous research is solved. sm.mousavi@shahed.ac.ir
Keywords :
Analysis of critical paths , Megaprojects , Interval type-2 fuzzy sets (IT2FSs) , Risk , Quality and safety factors
Journal title :
Journal of Optimization in Industrial Engineering
Serial Year :
2022
Record number :
2702677
Link To Document :
بازگشت