Abstract :
This paper describes the study made to assess the
electrical stresses imposed on line circuit breakers of a new
SOOkV, AC expansion of the FURNAS transmission system,
to be possibly installed in the Brazilian central region. The
study has considered three configurations of the transmission
lines, two of which assuming the use of compact towers. In
one of these two cases the lines would have high
surge-impedance loading. Digital simulations have been
made with the aid of the Alternative Transients Program
(ATP) to calculate the switching transients appearing as a
result of line energization and reclosing, clearing of terminal
and short-line faults, no-load line opening in normal and
faulted conditions, and out-of phase switching. Four
alternatives have been considered for the limitation of
overvoltages on closing, assuming either the sole use of surge
arresters on each line end or the use, in addition to the
arresters, of pre-insertion resistors, synchronizers or time
relays to provide a staggered closing of the breaker poles.
The stresses obtained were compared with those applied by
the standard IEC tests or with the maximum admissible
levels usually considered by the utility for its transmission
branches at the planning stage.