A dynamic model f or PERT risk evaluating in fuzzy environment
Author/Authors :
Mehrabadi، Hossein نويسنده ,
Issue Information :
روزنامه با شماره پیاپی سال 2011
Abstract :
n this paper we propose a dynamic model for evaluating of time risk in
stochastic network, where the activity durations are exponentionaly distributed
random variable and independent. We would like to present a new definition of
general risk index for project in each time and connect it to the notation of its
activity criticalities. We model such networks as finite-state, absorbing, and
continuous Marko chain with upper triangular generator matrices. The state
space is related to the network structure. The criticality index for each activity
will be computed and then we put forward a fuzzy way of measuring the
criticality to computing project states criticality. Then by using the probability of
absorption in each state severity of criticality will be computed dynamically. The
criticality measure obtained may serve as a measure of risk or of the supervision
effort needed by senior management. It also by ranking the states before project
initiating is able to forecast the critical states in order and help to the project
management to developing a proper guideline for resource planning and allocation.