Title of article :
Heuristic procedures for reactive project scheduling
Author/Authors :
Stijn Van de Vonder، نويسنده , , Francisco Ballest?n، نويسنده , , Erik Demeulemeester، نويسنده , , Willy Herroelen، نويسنده ,
Issue Information :
ماهنامه با شماره پیاپی سال 2007
Pages :
18
From page :
11
To page :
28
Abstract :
This paper describes new heuristic reactive project scheduling procedures that may be used to repair resource-constrained project baseline schedules that suffer from multiple activity duration disruptions during project execution. The objective is to minimize the deviations between the baseline schedule and the schedule that is actually realized. We discuss computational results obtained with priority-rule based schedule generation schemes, a sampling approach and a weighted-earliness tardiness heuristic on a set of randomly generated project instances.
Keywords :
Uncertainty , Stability , Project scheduling , Reactive scheduling
Journal title :
Computers & Industrial Engineering
Serial Year :
2007
Journal title :
Computers & Industrial Engineering
Record number :
925480