Power Limits of 220-Kv Transmission Lines
Author :
Kroneberg, Alex A. ; Macferran, Mabel
Author_Institution :
Southern Calif. Edison Co., Ltd., Los Angeles
Volume :
53
Issue :
12
fYear :
1934
Firstpage :
1794
Lastpage :
1802
Abstract :
For the transmission of power from Boulder Dam to the system of the Southern California Edison Company, numerous studies were made to determine the power limits of various designs of transmission lines, and the maximum generating capacity that could be installed safely at Boulder Dam without incurring instability. These studies were made for various design features and types of load and faults. The results of the studies are presented in this paper, a description of the method used being included in the appendixes.
Keywords :
Adders; Circuit faults; Circuit stability; Power generation; Power generation economics; Power system economics; Power transmission lines; Shafts;
fLanguage :
English
Journal_Title :
American Institute of Electrical Engineers, Transactions of the
Publisher :
ieee
ISSN :
0096-3860
Type :
jour
DOI :
10.1109/T-AIEE.1934.5056602
Filename :
5056602
Link To Document :