Title :
Facilities for the Supply of Kilowatts and Kilovars
Author :
Sels, Hollis K. ; Seely, Theodore
Author_Institution :
Transmission and substation engineer, Electric department of the Public Service Electric and Gas Company, Newark, N. J.
fDate :
5/1/1942 12:00:00 AM
Abstract :
Increased system kilowatt capacity may be realized by the reduction of generator kilovar requirements and the provision of reactive capacity sources at other points in the system. The factors to be considered in the choice of various reactive sources are discussed. Benefits to be realized from the various reactive sources are described. The paper is based upon system plan studies of a large eastern utility.
Keywords :
Capacity planning; Centralized control; Character generation; Circuit faults; Frequency; Power generation; Thermal loading; Thermal stability; Turbines; Voltage;
Journal_Title :
American Institute of Electrical Engineers, Transactions of the
DOI :
10.1109/T-AIEE.1942.5058523