Title :
Muskingum Unit No. 5 Auxiliary System
Author_Institution :
American Electric Power Service Corporation
Abstract :
The large units being installed today have auxiliary power requirements that exceed the capability of conventional auxiliary power systems. A study of the Tanners Creek unit of the American Electric Power Service Corporation was made to evaluate the design and formulate guidelines for future auxiliary bus designs. A complete analytical study was made, using pump and fan curves to determine expected auxiliary bus and equipment loadings.
Keywords :
Cooling; Economic forecasting; Guidelines; Power engineering and energy; Power generation; Power generation economics; Power system analysis computing; Power system economics; Satellites; Testing;
Journal_Title :
Power Apparatus and Systems, IEEE Transactions on
DOI :
10.1109/TPAS.1967.291931