Electrical Design and Testing of Cabin Creek Pumped-Storage Hydroelectric Project
Author
Robertson, Lawrence M. ; Burt, Lawrence S. ; Eastom, Frederick W. ; Hubbard, Clyde W. ; Brennan, Francis L. ; Fuller, Jackson F. ; Johrde, Paul S.
Author_Institution
Public Service Company of Colorado
Issue
3
fYear
1968
fDate
3/1/1968 12:00:00 AM
Firstpage
844
Lastpage
854
Abstract
The design, construction, and testing of one of the world´s highest altitude high head pumped-storage projects presented extraordinary challenges to equipment designers, project design and construction engineers, as well as the testing and operating engineers. Considerations are described that lead to the selection of the major equipment, including the demands of high altitude upon the electrical design criterion. The two generator/motors are believed to be the world´s largest 360 r/min synchronous machines. Special procedures for separate balancing of the generator/motor before coupling to the pump/turbine, and balancing techniques utilizing a full range of controlled speed balancing steps made possible by the wound rotor induction starting motor, have resulted in completed machines having exceptionally fine balance. The extensive instrumentation has provided not only a sound basis of testing during start-up, but also a complete hydraulic, mechanical, and electrical record of initial plant and system performance.
Keywords
Couplings; Design engineering; Induction generators; Induction motors; Magnetic heads; Pumps; Synchronous generators; Synchronous machines; Synchronous motors; Testing;
fLanguage
English
Journal_Title
Power Apparatus and Systems, IEEE Transactions on
Publisher
ieee
ISSN
0018-9510
Type
jour
DOI
10.1109/TPAS.1968.292200