• DocumentCode
    1045144
  • Title

    Project UHV.-Construction and Technical Plan

  • Author

    Anderson, John G. ; Doyle, Joseph R. ; O´Brien, E.J.

  • Author_Institution
    General Electric Company
  • Issue
    1
  • fYear
    1972
  • Firstpage
    204
  • Lastpage
    211
  • Abstract
    A description is given of the facilities at Project UHV for the study of EHV and UHV ac transmission problems up to 1500 kV. These facilities include a 1500/¿3 kV, single-phase autotransformer, a special 900-kV lightning arrester, and much associated UHV and EHV measuring equipment. Special stringing procedures are employed to string overhead test lines, and special test cages yield the corona characteristics of bundle conductors. Research is in progress on 1000 to 1500 kV transmission lines.
  • Keywords
    Arresters; Conductors; Contamination; Corona; Flashover; Insulation; Lightning; Testing; Transmission line measurements; Voltage;
  • fLanguage
    English
  • Journal_Title
    Power Apparatus and Systems, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0018-9510
  • Type

    jour

  • DOI
    10.1109/TPAS.1972.293332
  • Filename
    4074701