• DocumentCode
    1112864
  • Title

    Stability Studies and Tests on a 532-MW Cross-Compound Turbine-Generator Set

  • Author

    Ewart, D.N. ; Landgren, G.L. ; Temoshok, M. ; Walkley, W.W.

  • Author_Institution
    General Electric Company, Schenectady, N. Y.
  • Volume
    84
  • Issue
    4
  • fYear
    1965
  • fDate
    4/1/1965 12:00:00 AM
  • Firstpage
    338
  • Lastpage
    343
  • Abstract
    In the fall of 1963, two extended steady-state stability tests were conducted on a 532 000-kW cross-compound steam turbine-generator at the Will County Station of the Commonwealth Edison Company. These tests followed a series of analytical studies conducted from 1961 through 1963, and aimed at predicting extended steady-state stability limits. In the 1950s, similar tests had been conducted on smaller tandem steam turbine-generators and on hydrogenerators. The subject report is the first documentation of tests conducted on cross-compound turbine-generator sets. In addition, studies and tests were conducted to confirm steady-state stability limits in the generator overexcited region (lagging power factor operation). Operation in this region may occur with extra long transmission lines or weak interconnections between the unit and the power system.
  • Keywords
    Automatic voltage control; Documentation; Hydraulic turbines; Hydrogen; Power generation; Regulators; Shafts; Stability analysis; Steady-state; System testing;
  • fLanguage
    English
  • Journal_Title
    Power Apparatus and Systems, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0018-9510
  • Type

    jour

  • DOI
    10.1109/TPAS.1965.4766201
  • Filename
    4766201