Title :
A Fast Response Impulse Voltage Measuring System for Testing of Gas Insulated Substations Equipment
Author_Institution :
Department of Electrical Engineering Eindhoven University of Technology, Eindhoven, The Netherlands
fDate :
7/1/1986 12:00:00 AM
Abstract :
The step response characteristics of a single-capacitor, differentiating-integrating (DI) measuring system are outlined. This system has an intrinsic response time less than 1 ns. The factors influencing this very fast response when the system is incorporated in a large size GIS component are discussed. Further results demonstrate the application of the system for measurements on a GIS component with steep front-chopped impulse voltage with a rate of rise up to 2 kV/ns. The very fast response and the simplicity of this system offer a powerful measuring technique for impulse testing and fast transient measurements in GIS systems.
Keywords :
Capacitance measurement; Circuit testing; Dielectrics and electrical insulation; Gas insulation; Geographic Information Systems; Impulse testing; Inductance measurement; Substations; System testing; Voltage measurement;
Journal_Title :
Power Delivery, IEEE Transactions on
DOI :
10.1109/TPWRD.1986.4307973