• DocumentCode
    1148708
  • Title

    Fault Anticipator for Substation Equipment

  • Author

    Kurtz, M. ; Stone, G.C. ; Daechsel, P. ; Gupta, B.K.

  • Author_Institution
    Ontario Hydro Toronto, Canada
  • Volume
    2
  • Issue
    3
  • fYear
    1987
  • fDate
    7/1/1987 12:00:00 AM
  • Firstpage
    722
  • Lastpage
    724
  • Abstract
    Following an inordinate number of in-service failures of 230-kV current transformers, a need was perceived for some sort of early failure warning device for equipment in substations. The development and evaluation of an inexpensive partial discharge detection system for continuous on-line monitoring of substation equipment is described in this paper. The source of partial discharge activity, which nearly always precedes failure in high voltage equipment for times from minutes to months, may be unequivocally identified in a noisy substation environment, with no false alarms. Possible personnel hazard and damage to other equipment caused by an explosive failure can be avoided with appropriate operator action upon an alarm.
  • Keywords
    Acoustic noise; Circuit noise; Condition monitoring; Current transformers; Dielectric loss measurement; Dielectric measurements; Partial discharge measurement; Partial discharges; Substations; Working environment noise;
  • fLanguage
    English
  • Journal_Title
    Power Delivery, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0885-8977
  • Type

    jour

  • DOI
    10.1109/TPWRD.1987.4308169
  • Filename
    4308169