• DocumentCode
    1168394
  • Title

    Lifting of Transmission Towers Under Liver Line Conditions

  • Author

    Skelton, H.E. ; Orde, C.I.

  • Author_Institution
    Ontario Hydro
  • Issue
    9
  • fYear
    1982
  • Firstpage
    3018
  • Lastpage
    3021
  • Abstract
    To maintain adequate conductor ground clearance under emergency operating conditions, tower raising was required on existing double-circuit 230 kV transmission lines. A special tower lifting system was developed for raising towers while adding tower extensions all without de-energizing the lines. Since the method and equipment was unique, a major performance/acceptance test program was conducted which also served to confirm design assumptions. The system was demonstrated on a three-tower test line.
  • Keywords
    Conductors; Costs; Cranes; Distributed parameter circuits; Leg; Liver; Poles and towers; Security; Testing; Wind speed;
  • fLanguage
    English
  • Journal_Title
    Power Apparatus and Systems, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0018-9510
  • Type

    jour

  • DOI
    10.1109/TPAS.1982.317544
  • Filename
    4111701