DocumentCode
1182577
Title
Balance of System Costs for a 5 MW Photovoltaic Generating System
Author
Shushnar, G.J. ; Caldwell, J.H., Jr. ; Reinoehl, R.F. ; Wilson, J.H.
Author_Institution
ARCO Solar, Inc.
Issue
8
fYear
1985
Firstpage
2006
Lastpage
2011
Abstract
A cost study was conducted of a 12.2 million kWh/year (5 MW) photo- voltaic power plant of various configurations using actual data and experience from ARCO Solar´s large-scale PV´ projects in California. System costs were divided into PV costs and all BOS cost elements, which were grouped into area-related costs (inversely dependent on PV efficiency), power-related costs, and fixed costs. PV and area-related BOS costs make up 75% to 85% of total cost in all cases studied. Study results indicate the high sensitivity of BOS costs to PV efficiency, system configuration design, and BOS equipment design, and identify efficiency and configuration as the most effective avenues for BOS and system cost reduction.
Keywords
Costs; Inverters; Large-scale systems; Meeting planning; Performance analysis; Photovoltaic systems; Power & Energy Society; Power generation; Solar power generation; Terrorism;
fLanguage
English
Journal_Title
Power Apparatus and Systems, IEEE Transactions on
Publisher
ieee
ISSN
0018-9510
Type
jour
DOI
10.1109/TPAS.1985.318774
Filename
4113340
Link To Document