DocumentCode :
1183746
Title :
Parameters required to maximize a thermoset hydro-generator stator winding life. Part I-design, manufacture, installation
Author :
Lyles, John F. ; Goodeve, T. Earl ; Sedding, Howard
Author_Institution :
Ontario Hydro, Canada
Volume :
9
Issue :
3
fYear :
1994
fDate :
9/1/1994 12:00:00 AM
Firstpage :
620
Lastpage :
627
Abstract :
This paper describes the parameters required for a thermoset hydro-generator stator winding to achieve a service life of 50 years. Such parameters covering design, manufacture, installation, online monitoring and maintenance functions have been found to be relevant based on 36 years of design and operation experience. The database includes North American, European and Far Eastern hydro generators up to 20.5 kV-500 MVA. Parameters covered can be simply stated as design, installation and manufacture: the DIM rule
Keywords :
design engineering; electric breakdown of solids; hydroelectric generators; insulation testing; life testing; machine insulation; machine testing; maintenance engineering; manufacture; monitoring; stators; turbogenerators; 20.5 kV; 50 y; 500 MVA; DIM rule; database; design; hydroelectric generator; installation; maintenance; manufacture; online monitoring; operation experience; parameters; service life; stator winding; thermoset insulation life; Coils; Condition monitoring; Databases; Insulation; Pulp manufacturing; Rotating machines; Samarium; Stator windings; Stress; Voltage;
fLanguage :
English
Journal_Title :
Energy Conversion, IEEE Transactions on
Publisher :
ieee
ISSN :
0885-8969
Type :
jour
DOI :
10.1109/60.326483
Filename :
326483
Link To Document :