Abstract :
Simulation studies to reduce the number of link positions on an existing 275-kV cable route due for refurbishment are presented. This reduction in the number of link positions will effectively reduce the overall cost of maintenance and will also improve reliability. It is shown that the proposed layout and bonding arrangement can produce sheath voltages of up to 200 V during load conditions, 3 kV during external faults, and 6.4 kV during internal faults. Transient sheath to ground voltages of up to 100 kVp during lightning and up to 95 kVp during faults can be experienced. These voltages will be acceptable in normal service. The capital efficiency of the refurbishment, which reduces the number of link positions, should also reduce the risks of subsequent failure and the cost of maintenance.
Keywords :
EMTP; cable sheathing; digital simulation; maintenance engineering; power cables; transient analysis; 100 kV; 200 V; 275 kV; 3 kV; 6.4 kV; 95 kV; ATP; EMTP; bonding arrangement; capital efficiency; external faults; internal faults; layout; lightning; link positions reduction; load conditions; maintenance cost reduction; midlife cable refurbishment; reliability improvement; sheath voltage limiter; sheath voltages; transient sheath to ground voltages; Bonding; Cable shielding; Circuit faults; Costs; EMTP; Frequency; Insulation; Lightning; Maintenance; Voltage;
fLanguage :
English
Journal_Title :
Power Delivery, IEEE Transactions on
Publisher :
ieee
ISSN :
0885-8977
Type :
jour
DOI :
10.1109/TPWRD.2003.813632
Filename :
1208341
Link To Document :
بازگشت