  • Abstract
    A process for identifying specific opportunities for a utility´s implementation of microgrids is presented in the form of a process performed at an investor-owned electrical power utility in the Intermountain West. The paper provides the conditions, criteria, and constraints by which the study was conducted, it identifies specific scenarios and locations within the service territory by way of general conditions of viability, it addresses other possible scenarios and locations that are unique to the Company, and it provides a cost comparison example.
  • Keywords
    distributed power generation; electricity supply industry; Intermountain West; cost comparison example; investor-owned electrical power utility; microgrid implementation; power utility-owned microgrid; service territory; specific scenario selection; Companies; Fires; Generators; Interference; Microgrids; Substations; Vegetation; Business; microgrids; power distribution; power system economics; power system reliability;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    PES General Meeting | Conference & Exposition, 2014 IEEE
  • Conference_Location
    National Harbor, MD
  • Type

    conf

  • DOI
    10.1109/PESGM.2014.6938957
  • Filename
    6938957