  • Abstract
    The major postwar developments in the British overhead-transmission-line system consisted of the superposition of first 275kV lines, and secondly 400kV lines, on the original 132kV Grid system. The original lines were constructed with men or horses to tension conductors, and maintenance largely used manual tools. Today, highly specialised power-tensioning equipment is evolving, faults are electronically located, powerline patrol by helicopter is a regular procedure, and maintenance teams are in contact with each other and the system control by radio. Work is now being carried out on 275kV Grid lines in Scotland with all conductors alive. Many serious new mechanical problems are, however, still arising, even on the latest lines, and these are described, as are some of the means by which they are being overcome.
  • Keywords
    power transmission lines;
  • fLanguage
    English
  • Journal_Title
    Electrical Engineers, Proceedings of the Institution of
  • Publisher
    iet
  • ISSN
    0020-3270
  • Type

    jour

  • DOI
    10.1049/piee.1967.0177
  • Filename
    5248696