DocumentCode
1468659
Title
New blackstart standards needed for competitive markets
Author
Kirkby, B. ; Hirst, Eric
Author_Institution
Oak Ridge Lab., TN, USA
Volume
19
Issue
2
fYear
1999
fDate
2/1/1999 12:00:00 AM
Firstpage
9
Lastpage
11
Abstract
Restructuring the electric-power industry may present new challenges for bulk-power reliability. The incentives to maintain and properly deploy system blackstart services that worked for vertically integrated utilities may not work when the system operator, the transmission system, and individual generators are in separate commercial organizations. The four North American power system interconnections are designed to be in continuous synchronized operation. Individual pieces of equipment are taken out of service for maintenance, but each interconnection as a whole is designed to run without interruption. Nevertheless, the power system must be prepared for the rare occasions when all or a major portion of the system is forced out of service. The author reviews the existing standards for blackstart capability, standards for the restructured industry, and system blackstart under restructuring
Keywords
electricity supply industry; power system interconnection; power system reliability; power system restoration; standards; North American power system interconnections; blackstart capability; blackstart standards; bulk-power reliability; competitive markets; electric-power industry restructuring; restructured electricity industry; Control systems; Maintenance; Mesh generation; Power generation; Power system interconnection; Power system planning; Power system reliability; Power system restoration; Power system stability; System testing;
fLanguage
English
Journal_Title
Power Engineering Review, IEEE
Publisher
ieee
ISSN
0272-1724
Type
jour
DOI
10.1109/39.743417
Filename
743417