DocumentCode
1470551
Title
Substation distribution transformers failures and spares
Author
Kogan, V.I. ; Roeger, C.J. ; Tipton, D.E.
Author_Institution
American Electr. Power Service Corp., Columbus, OH, USA
Volume
11
Issue
4
fYear
1996
fDate
11/1/1996 12:00:00 AM
Firstpage
1905
Lastpage
1912
Abstract
Electric utilities should have a sufficient number of spare transformers to backup substation distribution transformers to replace transformers that fail and require factory rebuild or replacement. To identify such a number, the statistical methodology was developed to analyze available failure data for different groups of transformer. That methodology enables the estimation of future numbers of failures with associated probabilities, recommends the proper number of spares, identifies the necessity and shows the means to shorten the transformer´s replacement time
Keywords
distribution networks; failure analysis; probability; statistical analysis; transformer substations; failure data analysis; failure probabilities; spare transformers; statistical methodology; substation distribution transformers; transformer repair; transformer replacement; transformers failures; Cost function; Failure analysis; Power industry; Power supplies; Power system reliability; Production facilities; Senior members; Statistical analysis; Substations; Transformers;
fLanguage
English
Journal_Title
Power Systems, IEEE Transactions on
Publisher
ieee
ISSN
0885-8950
Type
jour
DOI
10.1109/59.544662
Filename
544662
Link To Document