    Impact of Premature Information Transfer on Cost and Development Time of Projects

  • Author

    Campos Silva, Daniel D. ; Santiago, Leonardo P. ; Silva, Daniel D Campos

  • Author_Institution
    Dept. of Production Eng., Fed. Univ. of Minas Gerais, Belo Horizonte, Brazil
  • Volume
    59
  • Issue
    4
  • fYear
    2012
  • Firstpage
    692
  • Lastpage
    704
  • Abstract
    The pressure to accelerate the transfer of information between tasks in order to reduce the duration of projects may lead to rework due to the uncertainty of data assertiveness. This paper assesses the impact of rework with regard to both a project´s costs and its duration. We have introduced a model that estimates the project development time by taking into account the premises of the task overlapping, the moment of information transfer, the risks of rework, and the consequences of the premature transfer of information. The model was used in the planning of a project for the construction of a fuel distribution terminal in a large Brazilian oil company. In this case, it was possible to demonstrate that the uncertainty derived from the premature transfer of information may increase a project´s duration and should be analyzed in the light of cost variations due to rework. The model determines the best moment in which to transmit information and assesses the impact of premature information transfer. More importantly, it demonstrates that the alternative to the early transfer of information does not necessarily result in a shorter project duration or in larger costs.
  • Keywords
    construction industry; costing; information management; planning; project management; recycling; Brazilian oil company; data assertiveness; fuel distribution terminal construction; premature information transfer; project cost; project development time; project planning; rework; Concurrent engineering; Minimization; Planning; Product development; Project management; Time factors; Uncertainty; Design structure matrix (DSM); probability of change and impact; project management; task overlap; time-cost tradeoffs;
  • fLanguage
    English
  • Journal_Title
    Engineering Management, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0018-9391
  • Type

    jour

  • DOI
    10.1109/TEM.2012.2187661
  • Filename
    6175943