    Expedient power line construction

  • Author

    Rorden, H. L.

  • Author_Institution
    Bonneville Power Administration, Portland, Oreg.
  • Volume
    66
  • Issue
    9
  • fYear
    1947
  • Firstpage
    884
  • Lastpage
    887
  • Abstract
    Material shortages during World War II imposed limitations on the construction of new transmission facilities and the Bonneville Power Administration conducted tests to determine minimum construction standards. Conductor diameter and spacing and insulation level involving losses, flashovers, safety to personnel working on energized lines, economic loading, and radio interference had to be considered.
  • Keywords
    Conductors; Corona; Noise; Poles and towers; Power transmission lines; Radio frequency; Transmission line measurements;